June 3, 2015
Beijing SOIL has acquired an order
from Ecuador's TP hydropower station and will supply a variety of instruments
such as “piezometer” and “earth pressure cell” to the TP hydropower station in
Ecuador.
Ecuador TP Dam
TP hydropower station is located in
Pichincha Province, Ecuador, belonging to high-altitude area. Diversion work
for two power generation projects, first grade hydropower station installed 49
MW and the second one installed 204 MW. Main buildings are as following:
16-kilometer diversion tunnel, concrete gravity dam(133-meter and 20-meter
height), underground plant and discharge tunnel, etc. Project was total
invested 269 million dollars, began to work in May 2011 and predicted to be
finished in 2016.
TOACHI dam was designed 59-meter high and
172.5-meter axis length. There are total 9 dam sections, all belonging to
concrete gravity dam. Total installed capacity is 254.4 thousand KW and
designed annual energy output is 1.1 billion KWH, is one of eight hydropower
stations in Ecuador under construction.